Most projects take 4–6 months end-to-end (varies by city/utility):
- Research & quotes: 1–2 months
- Contract → installation (design, permitting, scheduling): 2–3 months
- Utility interconnection: 2–4 weeks
Starting now gives you the best shot to finish before 12/31/2025.